What is the purpose of a punch list in ironwork projects?

  1. To finalize budget reports

  2. To identify remaining deficiencies

  3. To conduct employee evaluations

  4. To track deadline adherence

The correct answer is: To identify remaining deficiencies

The purpose of a punch list in ironwork projects is to identify remaining deficiencies. A punch list is a document used during the final stages of a construction project that outlines tasks that need to be completed or corrected before the project is considered finished. It typically includes items that do not meet the contract specifications, such as incomplete work or required repairs. Creating a punch list ensures that all aspects of the project are addressed, allowing for a thorough review before the final acceptance by the client or project owner. This helps to ensure quality control and satisfaction with the final product. By focusing on remaining issues, the punch list plays a critical role in completing the project to the required standards.